About the Project
ADDRESS Tom Thumb Road, Port Kembla
VALUE Stage 1 $25.8 million
Stage 2 $12.4 million
OVERVIEW
In October 2005 the NSW Government announced a $140 million development for Port Kembla.
Mainland Civil were the successful tenderer for the construction of stage 1 of a major component of the infrastructure works.
This stage consisted primarily of the construction of over 70,500m2 of heavy duty pavement, 113,500m2 of truck duty pavement and 8,500m2 of car duty pavement including all associated hydraulic, electrical and communication services.
By meeting the project’s tight programme requirements and consistently producing high quality finished work, Mainland Civil was able to negotiate the construction of the second stage including a further 153,000m2 of truck duty and car duty pavement.